In compliance to Regulation 30 of SEBI (Listing Obligations & Disclosure Requirements) Regulations, 2015, it is to inform that the third and last unit # III (110 MW) of Kishanganga HE Project situated at Jammu & Kashmir has been synchronized with grid on 30.03.2018. Unit# III has also successfully achieved its rated full load capacity at 23.58Hrs on 30.03.2018.
With the commissioning of above unit# III of Kishanganga HE Project, all three units (3X110 MW) of Kishanganga HE Project has been commissioned.
This is for your information and record.